This project details the highly specialized heavy lift logistics required for the successful transport of a massive 90 metric ton Manitowoc Lattice Boom Crawler Crane. Moving this huge piece of construction equipment required advanced hydraulic jacking techniques and a specialized Goldhofer trailer to ensure complete safety and precision.

Why does moving a 90 Metric Ton Crawler Crane demand expertise?

Crawler cranes like the MLC650 VPC MAX are essential for lifting massive loads on heavy construction sites. Because these machines are incredibly heavy and wide, transporting them requires specialized lifting and loading techniques. The width of 5.50 meters exceeds standard lane sizes. This makes standard loading ramps impossible to use.

Length: 12.00 meters
Width: 5.50 meters
Height: 4.00 meters
Weight: 90 metric tons

Standard loading methods are not safe for a 90 ton load with a width of 5.50 meters. We deployed advanced Hydraulic Jacks and a Goldhofer THP/SL modular trailer to securely manage the extreme weight.

  1. Precision Jacking Process: Our expert team used hydraulic jacks to carefully lift the crane to a height of 1.2 meters. We then securely rested the massive machine on strong steel supports.
  2. Trailer Positioning: Once the crane was completely stable on the supports, we positioned the Goldhofer hydraulic trailer directly beneath the load.
  3. Secure Loading and Offloading: The final step involved lifting the hydraulic trailer deck up to meet the crane. We ensured the cargo was securely loaded and lashed for transport. We repeated this exact same safe process for offloading at the destination.

The success of moving critical construction equipment relies on careful planning and execution.

This successful operation highlights the deep expertise of Three Lines Shipping in handling technically demanding heavy lift projects. We draw on over 20 years of specialized experience in project logistics. Our dedicated team consistently provides safe and on time solutions for the most complex cargo movements across the region. We ensure that your valuable industrial assets are transported with total precision and operational excellence.

Frequently Asked Questions on Crane Logistics

Let's Talk!

Get in touch with our team for all your queries.

Our Newsletter

Signup for Industry alerts, News & Insights

How We Transported 70 Ton CO2 Storage Tanks to Hassyan Power Plant

Reading Time: 2 minutes

How We Transported Four 85 MT Transformers to Hassyan Power Plant

Reading Time: 2 minutes

How We Jacked Up and Transported a 90 Ton Manitowoc Lattice Boom Crawler Crane

Reading Time: 2 minutes